Concept:Failing to deliver goods by the agreed date can amount to a breach of the contract.
Explanation:Chinyere promised to deliver the dress on September 20, 1995.
The date was a specific delivery date, so time was important to the agreement.
Because the dress was not ready by that date, Halima may treat the contract as broken by Chinyere.
Halima is not forced to wait or insist on the original promise.
She can choose to regard the contract as ended due to the breach.
Answer:B. Regard the contract between them as terminated.