Concept:Frustration terminates a contract when an unforeseen event makes further performance impossible.
Explanation:Mr Taiwo and Mr Bunmi had a valid contract for the hire of a car for two days.
The car was involved in an accident before the first day.
That accident was an unexpected event outside the control of either party.
It made the main purpose of the contract impossible to achieve.
Therefore, the contract was automatically brought to an end by frustration.
Mr Bunmi could not claim damages because neither party caused the failure.
The correct option is B. frustration.
Answer:B. frustration